Final Acceptance of Phases I & II CDQ Project at Hoa Phat Dung Quat Steel JSC Completed

View:60   Date:2021-04-23

The Phase II coke dry quenching project at Hoa Phat Dung Quat Steel JSC Ltd., undertaken by Huatai, received its final acceptance certificate on January 8, 2020, while the Phase I coke dry quenching project received its final acceptance certificate on January 30, 2021. The Phase II and Phase I coke dry quenching projects were successfully commissioned on August 31, 2019 and April 26, 2020, respectively.

CDQ Commissioning

Following an evaluation, all indicators for this project were rated excellent with high recognition from the client, and contract payments have been fully collected in stages.

This project was Huatai’s first CDQ project undertaken in Vietnam. With over 14,000 cubic meters of equipment and materials delivered, it marked the company’s first step in developing the Vietnamese market. The successful completion of this project has laid a solid foundation for Huatai to expand into more international markets in the future.

For this project listed as one of the company’s key projects, the company adhered to the principle of “Safety First, Quality First” throughout construction, establishing this project as another benchmark for the company. Leveraging its proven patented technologies and talented workforce, the company executed the project with great confidence, communicating promptly and effectively to resolve various issues raised by the client.

From the project’s inception to its completion, the company devoted considerable effort to its engineering design, equipment manufacturing and export, equipment installation, and technical services. As this was the company’s first overseas project, company leadership attached particular importance to it, and partner organizations provided the utmost cooperation. During construction, leaders at all levels of the company visited the site in person to provide guidance, demonstrating great care and support for the project.

Although the company faced various pressures during project execution, including unstable shipping schedules, complex construction conditions in Vietnam, and, particularly in the later stages, the outbreak of the pandemic, staff across all departments withstood the pressure, remained resident on-site, demonstrated great endurance and diligence and worked tirelessly, to ultimately ensure successful completion of the project.